A Temporary Certificate of Occupancy is typically issued for what maximum time period?
Correct Answer
C) 90 days
A Temporary Certificate of Occupancy is typically issued for a maximum of 90 days to allow occupancy while minor items are completed. Extensions may be possible but require justification and approval.
Why This Is the Correct Answer
A Temporary Certificate of Occupancy (TCO) is issued for a maximum of 90 days under Florida Building Code provisions. This timeframe allows property owners to occupy a building while completing minor finishing work or addressing non-critical code compliance items. The 90-day period provides sufficient time to resolve outstanding issues without creating undue hardship for occupants. Extensions beyond 90 days are possible but require formal application and justification to the building official.
Why the Other Options Are Wrong
Option A: 30 days
30 days is too short a timeframe for most construction projects to complete remaining work items that would warrant a TCO issuance.
Option B: 60 days
60 days, while closer to the correct answer, is still shorter than the standard 90-day maximum period established by the Florida Building Code.
Option D: 180 days
180 days (6 months) exceeds the standard maximum timeframe and would be considered an extension period rather than the initial TCO duration.
Memory Technique
Think '90 days = 3 months = 1 quarter year' - enough time to wrap up a construction project's final details but not so long that safety becomes a concern.
Reference Hint
Florida Building Code, Chapter 1, Section 110 - Certificate of Occupancy provisions
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A general contractor receives a change order request that will add $25,000 to the contract price and extend the completion date by 10 days. The contract allows for a 10% markup on change order work. What should be the total change order amount?
Next Question
Before a Certificate of Occupancy can be issued for a commercial building, which of the following must typically be completed?