EstatePass
law-businessCost Estimation & BiddingHARD

Under B&P Code 7028.15, when a California contractor submits a bid that includes both materials and labor, and the actual material costs increase by 25% after contract award due to market conditions, what is the contractor's legal obligation?

Correct Answer

C) The contractor must absorb all cost increases unless the contract includes an escalation clause

California law generally holds contractors to their bid prices unless specific contract provisions allow for adjustments. B&P Code 7028.15 emphasizes contractor responsibility for accurate bidding. Material cost escalation clauses must be explicitly included in contracts; otherwise, contractors bear the risk of cost increases in their estimation.

Answer Options
A
The contractor can abandon the project without penalty due to unforeseen circumstances
B
The contractor must renegotiate the contract with the owner
C
The contractor must absorb all cost increases unless the contract includes an escalation clause
D
The contractor can automatically pass through material cost increases exceeding 10%

Why This Is the Correct Answer

California law generally holds contractors to their bid prices unless specific contract provisions allow for adjustments. B&P Code 7028.15 emphasizes contractor responsibility for accurate bidding. Material cost escalation clauses must be explicitly included in contracts; otherwise, contractors bear the risk of cost increases in their estimation.

Was this explanation helpful?

More law-business Questions

Under B&P Code Section 7071.9, a contractor may deposit cash or securities instead of obtaining a surety bond. If a contractor chooses this option, where must the deposit be maintained and what happens to interest earned?

Under California's AB 5 law (Dynamex decision), which factor is NOT part of the ABC test for determining independent contractor status?

According to Business and Professions Code Section 7031, what is required when a licensed contractor supervises work performed by unlicensed employees on a construction project?

Under California Building Standards Code Title 24, which entity has the authority to issue building permits for most residential and commercial construction projects?

According to B&P Code 7159.5, service and repair contracts must include specific provisions. Which statement is correct regarding these contracts?

Which of the following activities is exempt from California contractor licensing requirements under Business and Professions Code Section 7048?

Under Cal/OSHA regulations in Title 8 CCR Section 5192, Safety Data Sheets (SDS) for hazardous chemicals used on construction sites must be readily accessible to employees during which hours?

Under California Business and Professions Code Section 7071.9, in lieu of a surety bond, what alternative security may a contractor provide to satisfy the contractor license bond requirement?

According to Cal/OSHA regulations, which of the following is NOT a required element of a written Injury and Illness Prevention Program (IIPP)?

A homeowner requests that a B-General Building Contractor provide a certificate of insurance naming the homeowner as an additional insured on the contractor's general liability policy. Under California law, what is the contractor's obligation?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.