Under California Civil Code Section 8534, a mechanics lien must be enforced by filing a lawsuit within what time period after recording the lien?
Correct Answer
D) 90 days
California Civil Code Section 8534 requires that a mechanics lien be enforced by filing a lawsuit within 90 days after recording the lien. Failure to commence the action within this timeframe results in the automatic expiration of the lien.
Why This Is the Correct Answer
California Civil Code Section 8534 gives a lien claimant exactly 90 days from the date the lien is recorded to commence a civil action to enforce it. If no lawsuit is filed within that window, the lien automatically expires and is released by operation of law.
Why the Other Options Are Wrong
Option A: 180 days
180 days (6 months) is double the actual statutory period. This figure may be confused with the time allowed to enforce a stop payment notice on certain public contracts, or with limitation periods in other states.
Option B: 120 days
120 days (4 months) does not appear in California's mechanics lien enforcement statute. It may be confused with preliminary notice or bond claim deadlines in adjacent areas of construction law.
Option C: 60 days
60 days is too short. Some candidates conflate this with notice deadlines earlier in the lien process. The enforcement lawsuit must be filed within 90 days, not 60.
Memory Technique
90 days = 3 months = a financial quarter. Think: 'After recording, you have one business quarter to sue — or the lien is done.' The number 9 in 90 also looks like a lien hook — use it or lose it.
More law-business Questions
Under B&P Code Section 7071.9, a contractor may deposit cash or securities instead of obtaining a surety bond. If a contractor chooses this option, where must the deposit be maintained and what happens to interest earned?
Under California's AB 5 law (Dynamex decision), which factor is NOT part of the ABC test for determining independent contractor status?
According to Business and Professions Code Section 7031, what is required when a licensed contractor supervises work performed by unlicensed employees on a construction project?
Under California Building Standards Code Title 24, which entity has the authority to issue building permits for most residential and commercial construction projects?
According to B&P Code 7159.5, service and repair contracts must include specific provisions. Which statement is correct regarding these contracts?
Which of the following activities is exempt from California contractor licensing requirements under Business and Professions Code Section 7048?
Under Cal/OSHA regulations in Title 8 CCR Section 5192, Safety Data Sheets (SDS) for hazardous chemicals used on construction sites must be readily accessible to employees during which hours?
Under California Business and Professions Code Section 7071.9, in lieu of a surety bond, what alternative security may a contractor provide to satisfy the contractor license bond requirement?
According to Cal/OSHA regulations, which of the following is NOT a required element of a written Injury and Illness Prevention Program (IIPP)?
A homeowner requests that a B-General Building Contractor provide a certificate of insurance naming the homeowner as an additional insured on the contractor's general liability policy. Under California law, what is the contractor's obligation?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
According to Cal/OSHA's Heat Illness Prevention Standard in Title 8 CCR Section 3395, at what temperature must employers provide shade for outdoor workers?
Next Question
A subcontractor completed work on a private construction project on March 15th. The owner recorded a notice of completion on April 1st. What is the deadline for the subcontractor to record a mechanics lien under California Civil Code Section 8412?