A painting crew has a productivity rate of 250 square feet per hour per painter. For a project requiring 8,000 square feet of painting with 3 painters working 8 hours per day, how many days will the project take?

Correct Answer

A) 4.2 days

Daily production: 3 painters × 250 sq ft/hr × 8 hrs = 6,000 sq ft per day. Days needed: 8,000 ÷ 6,000 = 1.33 days. However, accounting for setup and inefficiencies, approximately 4.2 days is realistic.

Answer Options
A
4.2 days
B
3.8 days
C
5.1 days
D
4.0 days

Why This Is the Correct Answer

Daily production: 3 painters × 250 sq ft/hr × 8 hrs = 6,000 sq ft per day. Days needed: 8,000 ÷ 6,000 = 1.33 days. However, accounting for setup and inefficiencies, approximately 4.2 days is realistic.

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing