A masonry crew can lay 400 concrete blocks per day. If a project requires 8,000 blocks and the crew costs $1,200 per day, what is the total labor cost for the masonry work?

Correct Answer

C) $24,000

Calculate days needed: 8,000 blocks ÷ 400 blocks per day = 20 days. Total labor cost: 20 days × $1,200 per day = $24,000.

Answer Options
A
$18,000
B
$20,400
C
$24,000
D
$28,800

Why This Is the Correct Answer

This is a straightforward productivity and cost calculation problem. First, we determine how many days the crew needs by dividing total blocks required (8,000) by daily production capacity (400 blocks/day) = 20 days. Then we multiply the number of days (20) by the daily crew cost ($1,200) to get the total labor cost of $24,000. This type of calculation is fundamental for estimating labor costs on construction projects.

Why the Other Options Are Wrong

Option A: $18,000

$18,000 would result from incorrectly calculating 15 days of work instead of 20 days, possibly from a math error in the division step.

Option B: $20,400

$20,400 appears to result from using 17 days instead of 20 days, which could come from rounding errors or miscalculation in the initial division.

Option D: $28,800

$28,800 would result from using 24 days instead of 20 days, possibly from incorrectly dividing 8,000 by 333 instead of 400 blocks per day.

Memory Technique

Remember 'WRT' - Work ÷ Rate = Time, then Time × Rate = Total cost. The rate appears in both calculations but in different positions.

Reference Hint

Construction estimating sections covering labor productivity rates and crew cost calculations, typically found in project management or estimating chapters.

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing