EstatePass
Project MgmtBlueprintseasy17% of exam part

A site plan shows existing grade at elevation 102.5' and proposed grade at elevation 104.2'. What is the amount of fill required at this location?

Correct Answer

A) 1.7 feet of fill

The fill required is calculated by subtracting existing grade from proposed grade: 104.2' - 102.5' = 1.7'. Since the result is positive, this indicates 1.7 feet of fill is needed to raise the grade.

Answer Options
A
1.7 feet of fill
B
1.7 feet of cut
C
206.7 feet total elevation
D
2.3 feet of fill

Why This Is the Correct Answer

To determine fill requirements, you subtract the existing grade elevation from the proposed grade elevation. When the proposed grade (104.2') is higher than the existing grade (102.5'), the positive result indicates fill is needed. The calculation 104.2' - 102.5' = 1.7' shows exactly how much fill material must be added to raise the ground to the desired elevation.

Why the Other Options Are Wrong

Option B: 1.7 feet of cut

This is incorrect because cut refers to removing soil when the proposed grade is lower than existing grade. Since 104.2' is higher than 102.5', we need to add material (fill), not remove it (cut).

Option C: 206.7 feet total elevation

This incorrectly adds the two elevations together (102.5' + 104.2' = 206.7'), which has no meaning in grading calculations. We need the difference between elevations, not their sum.

Option D: 2.3 feet of fill

This appears to be an incorrect calculation, possibly subtracting in the wrong direction or making an arithmetic error. The correct calculation is 104.2' - 102.5' = 1.7', not 2.3'.

Memory Technique

Think 'P-E=F/C' (Proposed minus Existing equals Fill or Cut). Positive result = Fill up, Negative result = Cut down.

Reference Hint

Look up site work and grading sections in construction reference materials, typically found in earthwork or site preparation chapters

More Project Mgmt Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing