In CPM scheduling, if Activity X has an early start of day 10, duration of 5 days, and late finish of day 18, what is the total float for this activity?
Correct Answer
D) 4 days
Early finish = Early start + Duration = 10 + 5 = 15. Total float = Late finish - Early finish = 18 - 15 = 3 days. However, this appears to be a calculation error in the explanation. Let me recalculate: Total float = Late finish - Early finish = 18 - 15 = 3 days, but the late start would be 18 - 5 = 13, so total float = 13 - 10 = 3 days.
Why This Is the Correct Answer
The correct answer is actually C) 3 days, not D) 4 days as stated. Total float represents the amount of time an activity can be delayed without affecting the project completion date. It's calculated as Late Finish - Early Finish, where Early Finish = Early Start + Duration = 10 + 5 = 15 days, and Total Float = 18 - 15 = 3 days. This can also be verified by calculating Late Start - Early Start = (18 - 5) - 10 = 13 - 10 = 3 days.
Why the Other Options Are Wrong
Option A: 1 day
1 day is incorrect because it significantly underestimates the available float time by 2 days
Option B: 2 days
2 days is incorrect because it underestimates the available float time by 1 day
Memory Technique
Remember 'LEAF' - Late minus Early equals Available Float (Late Finish - Early Finish = Total Float)
Reference Hint
Look up CPM scheduling and float calculations in Chapter 6 (Project Management) of the Florida General Contractor Reference Manual
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
In a Guaranteed Maximum Price (GMP) contract, the contractor's fee is $85,000 and the GMP is set at $1,200,000. If the actual project cost is $1,150,000, how much total compensation will the contractor receive assuming a 50/50 cost savings split?
Next Question
What is the typical range for contingency allowances on new commercial construction projects in Florida?