EstatePass
Contract AdminProceduresmedium13% of exam part

During construction, a mechanical contractor relocates ductwork 3 feet from its original design location to avoid a structural beam conflict. Who is typically responsible for updating the as-built drawings?

Correct Answer

C) The general contractor

The general contractor is typically responsible for coordinating and maintaining as-built documentation, including changes made by subcontractors. The GC collects information from all trades and ensures the as-builts are complete and accurate.

Answer Options
A
The architect
B
The structural engineer
C
The general contractor
D
The mechanical contractor who made the change

Why This Is the Correct Answer

CORRECT_ANSWER - The general contractor serves as the central coordinator for all construction activities and documentation. While individual subcontractors make field changes, the GC has the contractual responsibility to collect, coordinate, and maintain comprehensive as-built drawings from all trades. This ensures that all changes are properly documented in a unified set of drawings that reflects the actual constructed conditions across all building systems.

Why the Other Options Are Wrong

Option A: The architect

While the architect created the original design drawings, they are typically not on-site during construction and are not responsible for tracking field changes made by contractors. The architect's role is design-focused, not construction documentation.

Option B: The structural engineer

The structural engineer's responsibility is limited to structural design and engineering matters. They would not be responsible for documenting mechanical system changes, even if those changes were made to avoid structural conflicts.

Option D: The mechanical contractor who made the change

While the mechanical contractor made the physical change and should report it, they are only responsible for their specific trade work. They lack the authority and comprehensive view needed to maintain the complete as-built documentation for the entire project.

Memory Technique

Think 'GC = General Coordinator' - they coordinate all trades AND all documentation, making them responsible for as-builts regardless of who makes the changes.

Reference Hint

Florida Building Code, Chapter 1 - Administration and Enforcement, or AIA Contract Documents regarding contractor responsibilities

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing