During construction, a mechanical contractor relocates ductwork 3 feet from its original design location to avoid a structural beam conflict. Who is typically responsible for updating the as-built drawings?
Correct Answer
C) The general contractor
The general contractor is typically responsible for coordinating and maintaining as-built documentation, including changes made by subcontractors. The GC collects information from all trades and ensures the as-builts are complete and accurate.
Why This Is the Correct Answer
CORRECT_ANSWER - The general contractor serves as the central coordinator for all construction activities and documentation. While individual subcontractors make field changes, the GC has the contractual responsibility to collect, coordinate, and maintain comprehensive as-built drawings from all trades. This ensures that all changes are properly documented in a unified set of drawings that reflects the actual constructed conditions across all building systems.
Why the Other Options Are Wrong
Option A: The architect
While the architect created the original design drawings, they are typically not on-site during construction and are not responsible for tracking field changes made by contractors. The architect's role is design-focused, not construction documentation.
Option B: The structural engineer
The structural engineer's responsibility is limited to structural design and engineering matters. They would not be responsible for documenting mechanical system changes, even if those changes were made to avoid structural conflicts.
Option D: The mechanical contractor who made the change
While the mechanical contractor made the physical change and should report it, they are only responsible for their specific trade work. They lack the authority and comprehensive view needed to maintain the complete as-built documentation for the entire project.
Memory Technique
Think 'GC = General Coordinator' - they coordinate all trades AND all documentation, making them responsible for as-builts regardless of who makes the changes.
Reference Hint
Florida Building Code, Chapter 1 - Administration and Enforcement, or AIA Contract Documents regarding contractor responsibilities
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A building permit application fee is $1,850 plus $3.25 per $1,000 of construction value. If the project value is $485,000, what is the total permit fee?
Next Question
Building permit fees for a commercial project total $12,500. If the jurisdiction charges a 3.5% convenience fee for online payments and a 2.8% fee for credit card processing, what is the total amount due when paying online with a credit card?