When should as-built drawings be updated during construction?
Correct Answer
B) Continuously as changes occur
As-built drawings should be updated continuously as changes occur during construction to maintain accurate records. This ensures all modifications are properly documented and prevents information from being lost or forgotten.
Why This Is the Correct Answer
As-built drawings must be updated continuously as changes occur to maintain accurate documentation throughout the construction process. Waiting until later stages means critical details about modifications, field changes, and design adjustments could be forgotten or lost. Real-time updates ensure that all stakeholders have access to current information and that the final as-built drawings accurately reflect the completed project. This practice is essential for future maintenance, renovations, and compliance with building codes.
Why the Other Options Are Wrong
Option A: Only at project completion
Waiting until project completion to update as-built drawings is problematic because many construction details and change reasons will be forgotten by then, leading to incomplete or inaccurate documentation.
Option C: Monthly during progress meetings
Monthly updates during progress meetings are insufficient because many changes occur between meetings, and waiting a month to document modifications risks losing important details about the work performed.
Option D: When requested by the owner
Updating as-built drawings only when requested by the owner is inadequate because it makes the process reactive rather than proactive, potentially missing critical changes that occur when the owner isn't actively monitoring.
Memory Technique
Think 'ABC' - As-Built drawings need Continuous updates, not 'ABD' - As-Built at the enD
Reference Hint
Florida Building Code Chapter 1 - Administration and Enforcement, or AIA Contract Documents regarding record drawings and documentation requirements
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass