EstatePass
Contract AdminPreconstructionmedium27% of exam part

A contractor receives the following bids for sitework: $125,000, $118,000, $145,000, and $95,000. The engineer's estimate was $130,000. Which bid should receive the most scrutiny?

Correct Answer

D) $95,000 - significantly below others

The $95,000 bid is significantly below the engineer's estimate and other bids, suggesting possible errors, omissions, or unrealistic pricing that could lead to problems during construction.

Answer Options
A
$125,000 - closest to engineer's estimate
B
$118,000 - reasonable and competitive
C
$145,000 - highest bid received
D
$95,000 - significantly below others

Why This Is the Correct Answer

The $95,000 bid is approximately 27% below the engineer's estimate and 19% below the next lowest bid, which represents a significant deviation that warrants investigation. Such a large variance typically indicates potential errors in the bid calculation, missing scope items, or unrealistic pricing that could lead to change orders, delays, or contractor financial difficulties during construction. As a general contractor, scrutinizing unusually low bids protects against future project complications and ensures the subcontractor can actually perform the work as specified.

Why the Other Options Are Wrong

Option A: $125,000 - closest to engineer's estimate

While the $125,000 bid is closest to the engineer's estimate, being close to the estimate doesn't necessarily require additional scrutiny - it suggests the bid is reasonable and well-calculated.

Option B: $118,000 - reasonable and competitive

The $118,000 bid is within a reasonable range of the engineer's estimate (about 9% lower) and falls between other competitive bids, making it appear legitimate and not requiring special scrutiny.

Option C: $145,000 - highest bid received

Although the $145,000 bid is the highest, it's only about 12% above the engineer's estimate, which is within a reasonable variance range and doesn't necessarily indicate problems that require scrutiny.

Memory Technique

Use 'LOW = LOOK OUT WIDE' - when a bid is significantly LOW, LOOK OUT for problems and investigate WIDE-ranging potential issues

Reference Hint

Florida Building Code - Administration and Enforcement, Chapter on Contract Administration and Bidding Procedures

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing