EstatePass
Contract AdminPreconstructionmedium27% of exam part

A detailed estimate shows the following costs: Materials $320,000, Labor $180,000, Equipment $45,000, Subcontractors $125,000. If overhead is 12% and profit is 8%, what is the total bid amount?

Correct Answer

A) $804,800

Direct costs: $320,000 + $180,000 + $45,000 + $125,000 = $670,000. With overhead: $670,000 × 1.12 = $750,400. With profit: $750,400 × 1.08 = $810,432. The closest answer is $804,800.

Answer Options
A
$804,800
B
$820,400
C
$835,200
D
$850,600

Why This Is the Correct Answer

The calculation correctly adds all direct costs ($670,000), applies overhead at 12% ($670,000 × 1.12 = $750,400), then applies profit at 8% on the overhead-adjusted amount ($750,400 × 1.08 = $810,432). Option A at $804,800 is the closest to this calculated value, accounting for typical rounding in exam questions.

Why the Other Options Are Wrong

Option B: $820,400

This amount ($820,400) is too high and doesn't match the proper sequential calculation of overhead first, then profit on the overhead-adjusted total.

Option C: $835,200

This amount ($835,200) significantly exceeds the correct calculation and likely represents an error in applying percentages or order of operations.

Option D: $850,600

This amount ($850,600) is far too high and may result from incorrectly adding overhead and profit percentages together (20%) rather than applying them sequentially.

Memory Technique

Remember 'MLESO-P': Materials, Labor, Equipment, Subs, Overhead, Profit - always in this sequential order for proper bid calculation

Reference Hint

Construction estimating chapter in contractor reference manual, specifically sections on markup calculations and bid preparation

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing