A cost-plus contract has a fee of 8% and includes reimbursable costs of $750,000. If the contractor also incurs $25,000 in non-reimbursable costs, what is the contractor's total compensation?
Correct Answer
A) $810,000
In a cost-plus contract, the contractor receives reimbursement for allowable costs plus the agreed fee. Total compensation = $750,000 (reimbursable costs) + ($750,000 × 8% fee) = $750,000 + $60,000 = $810,000. Non-reimbursable costs are not included in compensation.
Why This Is the Correct Answer
In a cost-plus contract, the contractor's total compensation consists of two components: reimbursement for allowable costs and the agreed-upon fee percentage. The fee is calculated only on the reimbursable costs, not on non-reimbursable costs. Non-reimbursable costs are expenses the contractor must absorb and do not affect the compensation calculation. Therefore, total compensation = $750,000 (reimbursable costs) + $60,000 (8% fee on reimbursable costs) = $810,000.
Why the Other Options Are Wrong
Option B: $835,000
This incorrectly adds the non-reimbursable costs ($25,000) to the total compensation, but non-reimbursable costs are contractor expenses that are not covered by the owner.
Option C: $775,000
This only includes the reimbursable costs plus the non-reimbursable costs but fails to include the 8% fee that the contractor is entitled to receive.
Option D: $800,000
This adds the fee ($60,000) to the reimbursable costs but then subtracts the non-reimbursable costs, which is incorrect since non-reimbursable costs don't reduce compensation.
Memory Technique
Think 'Cost-Plus = Pay Back + Pay Extra' - you pay back allowable costs and pay extra (the fee), but you don't pay for what's not allowed (non-reimbursable costs)
Reference Hint
Florida Building Code, Chapter 4 - Contract Types and Payment Methods, or AIA Contract Documents section on Cost-Plus contracts
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
What information must be included in a Notice to Owner under Florida Statute 713.06?
Next Question
A change order increases the contract value by $75,000 and extends the completion date by 15 days. The original contract was $1,200,000 with a 120-day duration. What is the new contract value and duration?