During a framing inspection, the building inspector identifies several code violations. What is the contractor's next required step?
Correct Answer
B) Correct the violations and request a re-inspection
When violations are identified during an inspection, the contractor must correct all noted deficiencies and request a re-inspection before proceeding. Work cannot continue until the inspection passes.
Why This Is the Correct Answer
Option B is correct because Florida Building Code requires that all violations identified during inspections must be corrected before work can proceed to the next phase. The contractor is legally obligated to address deficiencies immediately and schedule a re-inspection to verify compliance. This ensures building safety and code compliance throughout the construction process. Continuing work without passing inspection can result in stop-work orders and additional penalties.
Why the Other Options Are Wrong
Option A: Continue with the next phase of construction and address violations later
Option A violates Florida Building Code requirements and can result in stop-work orders, fines, and legal liability. Continuing construction with known violations compromises structural integrity and safety, and inspectors have authority to halt all work until violations are corrected.
Option C: File an appeal with the building department
Option C is premature and unnecessary when violations are legitimate code deficiencies. Appeals are only appropriate when the contractor believes the inspector's findings are incorrect or when there are disputes about code interpretation, not for standard violation corrections.
Option D: Hire a third-party inspector to verify the work
Option D is not required and doesn't address the immediate need to correct violations. Third-party inspectors cannot override municipal building department authority, and the original inspector must verify that corrections meet code requirements through re-inspection.
Memory Technique
Use the acronym 'STOP': Stop work, Take corrective action, Obtain re-inspection, Proceed only after passing
Reference Hint
Florida Building Code Chapter 1 - Scope and Administration, Section 110 - Inspections; Florida Statutes Chapter 489 - Contracting
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A contractor submits an Application for Payment showing 60% completion on a $2,000,000 project. With 10% retainage, what amount should the contractor receive if this is the first payment application?
Next Question
During contract closeout, what document typically releases the contractor from further warranty obligations?