EstatePass
Contract AdminContractsmedium40% of exam part

A contractor submits an Application for Payment showing 60% completion on a $2,000,000 project. With 10% retainage, what amount should the contractor receive if this is the first payment application?

Correct Answer

A) $1,080,000

The work completed is $2,000,000 × 60% = $1,200,000. With 10% retainage held, the payment is $1,200,000 × 90% = $1,080,000. Since this is the first payment application, no previous payments are deducted.

Answer Options
A
$1,080,000
B
$1,200,000
C
$1,080,000 minus previous payments
D
$1,200,000 minus previous payments

Why This Is the Correct Answer

Option A is correct because it properly calculates the net payment amount for the first application. The contractor has completed 60% of $2,000,000 worth of work ($1,200,000), but the owner retains 10% of that amount ($120,000) as retainage. Therefore, the contractor receives $1,200,000 - $120,000 = $1,080,000. Since this is the first payment application, there are no previous payments to subtract from this amount.

Why the Other Options Are Wrong

Option B: $1,200,000

Option B fails to account for retainage. While $1,200,000 represents the value of work completed (60% of $2,000,000), the contractor cannot receive the full amount because the owner must withhold 10% retainage ($120,000) until project completion or substantial completion.

Option C: $1,080,000 minus previous payments

Option C incorrectly suggests subtracting previous payments when the problem clearly states this is the first payment application. There are no previous payments to deduct, making this calculation method inappropriate for this scenario.

Option D: $1,200,000 minus previous payments

Option D makes two errors: it fails to deduct retainage from the work completed value, and it unnecessarily references previous payments when this is explicitly the first payment application with no prior payments to subtract.

Memory Technique

Remember 'FIRST = Fresh start, no previous payments' and 'Retainage Always Retained' - so for first payments, just calculate completed work minus retainage percentage.

Reference Hint

AIA Document A201 General Conditions, Article 9 - Payments and Completion, specifically sections on Applications for Payment and retainage provisions

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing