A payment bond claim must be filed within how many days after the claimant's last day of work under typical bond provisions?
Correct Answer
B) 90 days
Most payment bonds require claims to be filed within 90 days after the claimant's last day of providing labor or materials. This timeframe is typically shorter than lien deadlines and must be strictly observed.
Why This Is the Correct Answer
Payment bond claims must typically be filed within 90 days after the claimant's last day of providing labor or materials to the project. This 90-day requirement is a standard provision found in most payment bonds and is established to provide a reasonable but limited timeframe for claimants to assert their rights. The deadline is strictly enforced by courts, and failure to file within this period generally results in the complete loss of the right to make a claim against the bond. This timeframe balances the need to give subcontractors and suppliers adequate time to file claims while also providing certainty to sureties about their potential exposure.
Why the Other Options Are Wrong
Option A: 60 days
60 days is too short and not the standard timeframe established in typical payment bond provisions for filing claims.
Option C: 120 days
120 days exceeds the standard payment bond claim filing period and confuses this deadline with other construction-related timeframes.
Option D: 180 days
180 days is far too long and may confuse this deadline with certain lien deadlines, but payment bond claims have much shorter filing requirements.
Memory Technique
Think '90 days for bond claims' - remember that bonds are 'quicker to expire' than liens, so you need to act faster (90 vs longer lien periods).
Reference Hint
Florida Construction Law and Lien Law chapter, specifically sections covering payment bonds and surety obligations
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass