A payment bond claim must be filed within how many days after the claimant's last day of work under typical bond provisions?

Correct Answer

B) 90 days

Most payment bonds require claims to be filed within 90 days after the claimant's last day of providing labor or materials. This timeframe is typically shorter than lien deadlines and must be strictly observed.

Answer Options
A
60 days
B
90 days
C
120 days
D
180 days

Why This Is the Correct Answer

Payment bond claims must typically be filed within 90 days after the claimant's last day of providing labor or materials to the project. This 90-day requirement is a standard provision found in most payment bonds and is established to provide a reasonable but limited timeframe for claimants to assert their rights. The deadline is strictly enforced by courts, and failure to file within this period generally results in the complete loss of the right to make a claim against the bond. This timeframe balances the need to give subcontractors and suppliers adequate time to file claims while also providing certainty to sureties about their potential exposure.

Why the Other Options Are Wrong

Option A: 60 days

60 days is too short and not the standard timeframe established in typical payment bond provisions for filing claims.

Option C: 120 days

120 days exceeds the standard payment bond claim filing period and confuses this deadline with other construction-related timeframes.

Option D: 180 days

180 days is far too long and may confuse this deadline with certain lien deadlines, but payment bond claims have much shorter filing requirements.

Memory Technique

Think '90 days for bond claims' - remember that bonds are 'quicker to expire' than liens, so you need to act faster (90 vs longer lien periods).

Reference Hint

Florida Construction Law and Lien Law chapter, specifically sections covering payment bonds and surety obligations

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing