During bid evaluation, a contractor finds that all electrical subcontractor bids exclude temporary power costs estimated at $8,500. The selected electrical bid is $67,200. What should be included in the project estimate for electrical work?
Correct Answer
C) $67,200 plus a separate line item for temporary power
The estimate should include the subcontractor bid amount plus a separate line item for the excluded temporary power costs to ensure all electrical work is covered in the project budget.
Why This Is the Correct Answer
Option C is correct because proper project estimating requires transparency and completeness in cost tracking. When subcontractor bids exclude specific costs, the general contractor must account for those costs separately to ensure full project coverage. Creating a separate line item for the $8,500 temporary power costs maintains clear cost accountability and ensures nothing is overlooked during project execution. This approach also helps with change order management if temporary power requirements change during construction.
Why the Other Options Are Wrong
Option A: $67,200
Option A only includes the base electrical bid of $67,200 but completely ignores the excluded temporary power costs of $8,500, which would result in an incomplete project estimate and potential cost overruns.
Option B: $75,700
Option B simply adds the temporary power cost to the electrical bid ($67,200 + $8,500 = $75,700) but fails to maintain the important separate line item tracking that distinguishes between the subcontractor's scope and additional contractor responsibilities.
Option D: $58,700
Option D incorrectly subtracts the temporary power cost from the electrical bid ($67,200 - $8,500 = $58,700), which makes no logical sense since temporary power is an additional cost requirement, not a credit or reduction.
Memory Technique
Remember 'SEPARATE the EXCLUDED' - when subs exclude costs, always separate those costs as distinct line items rather than bundling them together for better project cost control.
Reference Hint
Florida Building Construction Standards and Practices - Chapter on Project Estimating and Bid Analysis, or Construction Project Management references covering subcontractor bid evaluation procedures.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
According to Florida Statutes, what must be established for liquidated damages to be enforceable in a construction contract?
Next Question
A subcontractor agreement includes an indemnification clause requiring the subcontractor to hold harmless the general contractor. This clause primarily protects the general contractor from: