According to AIA Document A201, General Conditions of the Contract for Construction, who has the authority to reject work that does not conform to the contract documents?
Correct Answer
C) The architect only
Under AIA A201, the architect has the authority to reject work that does not conform to the contract documents. The architect acts as the owner's representative in reviewing and approving work quality and compliance.
Why This Is the Correct Answer
Under AIA Document A201, the architect is specifically granted the authority to reject work that does not conform to the contract documents. This authority is part of the architect's role as the owner's representative for construction administration. The architect has the responsibility to review the contractor's work for compliance with the contract documents and can reject non-conforming work. This authority is clearly defined in the general conditions and is a key aspect of the architect's construction phase services.
Why the Other Options Are Wrong
Option A: The owner only
While the owner ultimately has rights regarding their project, under AIA A201 the owner delegates the authority to reject non-conforming work to the architect. The owner does not directly exercise this authority during construction administration.
Option B: The contractor only
The contractor does not have the authority to reject work under AIA A201. The contractor's role is to perform the work in accordance with the contract documents, not to determine whether work conforms to those documents.
Option D: Both the architect and the owner
While both the architect and owner may have concerns about non-conforming work, AIA A201 specifically grants this authority to the architect alone as part of their construction administration duties. The owner has delegated this authority to the architect.
Memory Technique
Think 'A for Architect, A for Authority' - the architect has the authority to reject work under AIA documents as the owner's representative.
Reference Hint
AIA Document A201 - General Conditions of the Contract for Construction, Section 4 (Administration of the Contract) regarding the architect's authority and responsibilities
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass