A project has the following activities: A(4 days) → B(6 days) → D(3 days) and A(4 days) → C(8 days) → D(3 days). Activity D cannot start until both B and C are complete. What is the critical path duration?
Correct Answer
B) 15 days
Path 1: A(4) + B(6) + D(3) = 13 days. Path 2: A(4) + C(8) + D(3) = 15 days. The critical path is the longest path, which is 15 days through A-C-D.
Why This Is the Correct Answer
The critical path is the longest sequence of activities that determines the minimum project duration. In this network, there are two possible paths from start to finish: A-B-D (13 days) and A-C-D (15 days). Since Activity D cannot start until both B and C are complete, we must wait for the longer path (A-C-D) to finish before D can begin. Therefore, the critical path duration is 15 days.
Why the Other Options Are Wrong
Option A: 13 days
13 days represents only the duration of path A-B-D, but this ignores the constraint that Activity D cannot start until both B and C are complete. Since path A-C-D takes 15 days, D cannot actually start after only 13 days.
Option C: 17 days
17 days is incorrect as it doesn't correspond to any valid path calculation in this network. The longest path A-C-D only totals 15 days (4+8+3), not 17 days.
Option D: 19 days
19 days is incorrect as it exceeds any possible path duration in this network. This might result from incorrectly adding all activity durations together (4+6+8+3=21) rather than following the actual network logic.
Memory Technique
Remember 'LONGEST = CRITICAL' - the critical path is always the longest duration path through your project network, as it controls when your project can finish.
Reference Hint
Look up 'Critical Path Method (CPM)' and 'Project Scheduling' in construction management chapters, typically found in project management or scheduling sections of contractor reference materials.
More Business & Finance Questions
A contractor's license expires on March 31st. If they submit a renewal application on April 15th, what additional requirement must be met under Florida regulations?
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
In Florida, what is the minimum workers' compensation insurance coverage required for construction companies with employees?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
People Also Study
Previous Question
A Florida contractor's SUTA rate is 2.7% on the first $7,000 of wages per employee. With 8 employees each earning over $7,000 annually, what is the total SUTA liability?
Next Question
During a performance evaluation, a supervisor documents that an employee 'needs improvement in punctuality and attention to detail.' What is the most important next step in the evaluation process?