EstatePass
Contract AdminProcedureseasy13% of exam part

What information is typically NOT included in as-built drawings?

Correct Answer

C) Original design specifications that were not modified

As-built drawings document the actual constructed conditions, including changes from the original design. Original design specifications that were not modified during construction would not be specifically noted on as-built drawings.

Answer Options
A
Actual locations of underground utilities
B
Field changes made during construction
C
Original design specifications that were not modified
D
Final elevations and dimensions as constructed

Why This Is the Correct Answer

As-built drawings are specifically created to document what was actually constructed, not what was originally planned. Their primary purpose is to show deviations, changes, and field modifications from the original design. Original design specifications that remained unchanged during construction are already documented in the original construction drawings and do not need to be re-documented in as-built drawings. As-built drawings focus on capturing the differences between what was planned and what was actually built.

Why the Other Options Are Wrong

Option A: Actual locations of underground utilities

Actual locations of underground utilities are a critical component of as-built drawings because utilities are often relocated during construction due to field conditions, conflicts, or unforeseen obstacles. These actual locations differ from the original design and must be documented for future reference.

Option B: Field changes made during construction

Field changes made during construction are the primary reason as-built drawings exist. These drawings specifically document all modifications, substitutions, and changes that occurred during the construction process that deviate from the original plans.

Option D: Final elevations and dimensions as constructed

Final elevations and dimensions as constructed are essential elements of as-built drawings, especially when they differ from the original design due to field conditions, grade changes, or construction modifications. These actual measurements are crucial for future maintenance and renovations.

Memory Technique

Think 'AS-BUILT = AS-CHANGED' - these drawings only capture what was built differently than originally planned, not what remained the same.

Reference Hint

Florida Building Code, Chapter 1 - Administration and Enforcement, or AIA Contract Documents regarding record drawings and as-built requirements

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing