What information is typically NOT included in as-built drawings?
Correct Answer
C) Original design specifications that were not modified
As-built drawings document the actual constructed conditions, including changes from the original design. Original design specifications that were not modified during construction would not be specifically noted on as-built drawings.
Why This Is the Correct Answer
As-built drawings are specifically created to document what was actually constructed, not what was originally planned. Their primary purpose is to show deviations, changes, and field modifications from the original design. Original design specifications that remained unchanged during construction are already documented in the original construction drawings and do not need to be re-documented in as-built drawings. As-built drawings focus on capturing the differences between what was planned and what was actually built.
Why the Other Options Are Wrong
Option A: Actual locations of underground utilities
Actual locations of underground utilities are a critical component of as-built drawings because utilities are often relocated during construction due to field conditions, conflicts, or unforeseen obstacles. These actual locations differ from the original design and must be documented for future reference.
Option B: Field changes made during construction
Field changes made during construction are the primary reason as-built drawings exist. These drawings specifically document all modifications, substitutions, and changes that occurred during the construction process that deviate from the original plans.
Option D: Final elevations and dimensions as constructed
Final elevations and dimensions as constructed are essential elements of as-built drawings, especially when they differ from the original design due to field conditions, grade changes, or construction modifications. These actual measurements are crucial for future maintenance and renovations.
Memory Technique
Think 'AS-BUILT = AS-CHANGED' - these drawings only capture what was built differently than originally planned, not what remained the same.
Reference Hint
Florida Building Code, Chapter 1 - Administration and Enforcement, or AIA Contract Documents regarding record drawings and as-built requirements
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass