During bid preparation, a contractor discovers a significant discrepancy between the plans and specifications. What is the most appropriate course of action?
Correct Answer
C) Submit a Request for Information (RFI) to clarify the discrepancy
When discrepancies exist between plans and specifications, the proper procedure is to submit an RFI to the owner or architect for clarification. This ensures accurate bidding and prevents disputes during construction.
Why This Is the Correct Answer
Submitting an RFI (Request for Information) is the proper professional procedure when discrepancies exist between plans and specifications during bid preparation. This formal process ensures all bidders receive the same clarification, maintains fairness in the bidding process, and prevents costly disputes or change orders during construction. The RFI allows the design team to provide official clarification that becomes part of the contract documents.
Why the Other Options Are Wrong
Option A: Submit the bid based on the plans only
Submitting a bid based only on the plans while ignoring conflicting specifications creates significant risk for the contractor and could lead to disputes, change orders, or legal issues during construction when the specifications must also be followed.
Option B: Submit the bid based on the specifications only
Submitting a bid based only on the specifications while ignoring conflicting plans is equally problematic, as both documents are typically part of the contract and the contractor would be obligated to follow both, creating potential conflicts during construction.
Option D: Include an allowance in the bid to cover potential issues
Including an allowance without seeking clarification is unprofessional and risky, as it doesn't resolve the actual discrepancy and may result in an uncompetitive bid or insufficient funds to cover the actual requirements once the discrepancy is resolved.
Memory Technique
Think 'RFI before you FLY' - always Request For Information before you submit your bid when there are discrepancies
Reference Hint
Florida Building Code Administration chapter or AIA General Conditions sections dealing with contract document interpretation and RFI procedures
More Business & Finance Questions
A contractor's license expires on March 31st. If they submit a renewal application on April 15th, what additional requirement must be met under Florida regulations?
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
In Florida, what is the minimum workers' compensation insurance coverage required for construction companies with employees?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
People Also Study
Previous Question
A construction company purchases a crane for $350,000. Using the Modified Accelerated Cost Recovery System (MACRS) with a 5-year recovery period, what is the depreciation deduction for the second year if the MACRS percentage for year 2 is 32%?
Next Question
According to OSHA 29 CFR 1926, at what height must fall protection be provided for employees working on scaffolds?