You are reviewing shop drawings for structural steel that show connection details different from the original design drawings. What is the most appropriate action?

Correct Answer

C) Submit the shop drawings to the structural engineer for review and approval

Shop drawings that deviate from the original design must be submitted to the design professional (structural engineer) for review and approval. The engineer must verify that the proposed changes maintain structural integrity and code compliance.

Answer Options
A
Proceed with construction as the shop drawings are more detailed
B
Return the shop drawings to the fabricator for correction without review
C
Submit the shop drawings to the structural engineer for review and approval
D
Use the original design drawings and ignore the shop drawing details

Why This Is the Correct Answer

When shop drawings deviate from the original design, the structural engineer who sealed the original plans must review and approve any changes to ensure structural integrity and code compliance. The engineer is the only qualified professional who can determine if the proposed connection details will perform adequately under the design loads. This protects both the contractor and owner from potential structural failures and maintains the engineer's professional responsibility for the design.

Why the Other Options Are Wrong

Option A: Proceed with construction as the shop drawings are more detailed

Shop drawings being more detailed does not automatically make them correct or safe. The fabricator may have made changes for convenience or cost savings that could compromise structural performance, so engineering review is still required.

Option B: Return the shop drawings to the fabricator for correction without review

Simply returning the drawings without proper engineering review assumes the changes are wrong, but they may actually be acceptable alternatives that could save time or money if properly evaluated by the engineer.

Option D: Use the original design drawings and ignore the shop drawing details

Ignoring shop drawing details could lead to field conflicts, construction delays, and potential safety issues if the fabricator has identified legitimate concerns with the original design that need to be addressed.

Memory Technique

Think 'SEAL' - when Structural Elements Are aLtered, the engineer who sealed the original design must approve changes

Reference Hint

Florida Building Code Chapter 17 - Structural Tests and Special Inspections, and AIA A201 General Conditions regarding shop drawing review procedures