Your company is bidding on a public project and discovers an error in the bid documents after submission but before bid opening. What is the most appropriate course of action?

Correct Answer

B) Contact the owner immediately to request bid withdrawal

For public projects, contractors should immediately contact the owner to request bid withdrawal when errors are discovered after submission. Most public entities have procedures allowing bid withdrawal before opening when mathematical or clerical errors can be demonstrated.

Answer Options
A
Wait until after award to address the error
B
Contact the owner immediately to request bid withdrawal
C
Submit a revised bid before the deadline
D
Honor the original bid regardless of the error

Why This Is the Correct Answer

Option B is correct because Florida public procurement law and most public entities have established procedures that allow contractors to withdraw bids before opening when demonstrable errors are discovered. Immediate notification protects both the contractor from potential financial loss and the public entity from complications that could arise from an erroneous bid. This process maintains the integrity of the competitive bidding process while providing a fair remedy for genuine mistakes.

Why the Other Options Are Wrong

Option A: Wait until after award to address the error

Waiting until after award creates significant legal and financial complications, as the contractor may be bound by the bid and face penalties for non-performance or breach of contract.

Option C: Submit a revised bid before the deadline

Once a bid is submitted, it cannot be revised or resubmitted - this would violate public bidding procedures and compromise the competitive process integrity.

Option D: Honor the original bid regardless of the error

Honoring an erroneous bid could result in substantial financial loss to the contractor and may lead to project performance issues or potential bankruptcy, which ultimately harms the public project.

Memory Technique

Remember 'BITE' - Before opening, Immediate contact, Tell the owner, Error withdrawal allowed

Reference Hint

Florida Statutes Chapter 255 - Public Construction Contracting, specifically sections on bid procedures and withdrawal provisions

More Business & Finance Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing