EstatePass
Contract AdminPreconstructionhard27% of exam part

A roofing crew's productivity rate is 25 squares per day in good weather but drops to 18 squares per day in adverse conditions. For a 450-square roof project scheduled during hurricane season, what is the estimated duration accounting for weather delays?

Correct Answer

C) 25 days

Using reduced productivity rate for hurricane season: 450 squares ÷ 18 squares per day = 25 days. This accounts for expected weather-related delays during the vulnerable season.

Answer Options
A
18 days
B
22 days
C
25 days
D
30 days

Why This Is the Correct Answer

Option C is correct because during hurricane season, contractors must plan using the reduced productivity rate of 18 squares per day rather than the optimal 25 squares per day. The calculation is straightforward: 450 total squares ÷ 18 squares per day = 25 days. This conservative approach accounts for the expected weather delays and interruptions that are common during Florida's hurricane season from June through November.

Why the Other Options Are Wrong

Option A: 18 days

Option A (18 days) incorrectly uses the good weather productivity rate of 25 squares per day (450 ÷ 25 = 18), which fails to account for the weather delays expected during hurricane season.

Option B: 22 days

Option B (22 days) appears to use an incorrect productivity rate or calculation method that doesn't align with either the good weather rate (25 squares/day) or the adverse weather rate (18 squares/day) provided in the problem.

Option D: 30 days

Option D (30 days) overestimates the project duration and doesn't correspond to any logical calculation using the given productivity rates of 25 or 18 squares per day.

Memory Technique

Remember 'Hurricane = Harder work' - always use the lower (adverse weather) productivity rate when scheduling during Florida's hurricane season (June-November).

Reference Hint

Florida Building Code Chapter 15 - Roof Assemblies and Rooftop Structures, and project scheduling sections in construction management references

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing