Contract AdminProceduresmedium13% of exam part

During construction, the electrical contractor relocates a panel 3 feet from its original location due to a structural conflict. The change was approved verbally by the architect. What documentation should the general contractor ensure is completed?

Correct Answer

D) All of the above

All documentation is important: written confirmation protects against future disputes, meeting minutes provide a timeline record, and as-built drawings ensure the accurate location is recorded for future reference. Comprehensive documentation is essential for project management.

Answer Options
A
Update the as-built drawings to show the new panel location
B
Obtain written confirmation of the change from the architect
C
Document the change in the project meeting minutes
D
All of the above

Why This Is the Correct Answer

Option D is correct because comprehensive documentation is essential for proper project management and legal protection. Each type of documentation serves a specific purpose: written confirmation from the architect provides legal protection against future disputes about the approved change, meeting minutes establish a timeline and record of the decision-making process, and as-built drawings ensure accurate location documentation for future maintenance, renovations, or emergencies. All three forms of documentation work together to create a complete record of the change.

Why the Other Options Are Wrong

Option A: Update the as-built drawings to show the new panel location

This option is incomplete - while updating as-built drawings is important for future reference, it alone doesn't provide adequate documentation for a change order situation.

Option B: Obtain written confirmation of the change from the architect

This option is incomplete - while written confirmation is crucial for legal protection, it doesn't address the need for as-built documentation or meeting records.

Option C: Document the change in the project meeting minutes

This option is incomplete - while meeting minutes provide timeline documentation, they don't replace the need for formal written confirmation or updated drawings.

Memory Technique

Remember 'CMA' - Confirmation (written), Minutes (meeting records), and As-builts (drawings) - all three are needed for complete change documentation.

Reference Hint

Florida Building Code Chapter 1 - Administration and Enforcement, and AIA Contract Documents regarding change orders and documentation requirements