During contract administration, you discover a discrepancy between the plans and specifications. What is the proper procedure?

Correct Answer

B) Submit a Request for Information (RFI) to the architect/engineer

When discrepancies exist between contract documents, the proper procedure is to submit an RFI to the design professional for official clarification before proceeding with work.

Answer Options
A
Proceed with construction using your best judgment
B
Submit a Request for Information (RFI) to the architect/engineer
C
Choose the most cost-effective interpretation
D
Contact the owner directly for clarification

Why This Is the Correct Answer

Submitting an RFI to the architect/engineer is the proper procedure because they are the design professionals who created the contract documents and have the authority to interpret them. This formal process ensures that any clarification is documented, legally binding, and maintains the chain of responsibility. The RFI process protects all parties by creating a paper trail and ensures that the resolution comes from the appropriate authority who understands the design intent.

Why the Other Options Are Wrong

Option A: Proceed with construction using your best judgment

Proceeding with construction using your best judgment is dangerous and potentially costly because it assumes liability for interpretation without proper authority. If your judgment proves incorrect, you could be responsible for costly rework, delays, and potential legal issues.

Option C: Choose the most cost-effective interpretation

Choosing the most cost-effective interpretation prioritizes economics over design intent and proper procedure. This approach could result in work that doesn't meet the owner's requirements or the design professional's intent, leading to rejection of work and costly corrections.

Option D: Contact the owner directly for clarification

Contacting the owner directly bypasses the design professional who has the technical expertise and legal authority to interpret the contract documents. The owner typically lacks the technical knowledge to resolve design discrepancies and may not have the authority to make binding interpretations.

Memory Technique

Remember 'RFI before you FLY' - always submit a Request for Information before proceeding when there are discrepancies, or your project might crash and burn.

Reference Hint

AIA General Conditions, Section 3.2.4 - Contractor's responsibilities for reviewing contract documents and requesting clarification

More Business & Finance Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing