Which AIA document serves as the standard form of agreement between owner and contractor for construction projects?
Correct Answer
B) AIA A101 - Owner-Contractor Agreement
AIA A101 is the standard form of agreement between owner and contractor. AIA A201 contains the general conditions that supplement the agreement, while A401 is used for contractor-subcontractor relationships.
Why This Is the Correct Answer
AIA A101 is specifically designed as the standard form of agreement between owner and contractor for construction projects. This document establishes the contractual relationship, defines the scope of work, contract price, and time for completion. It serves as the primary contract document that binds the owner and contractor together legally. The A101 form is widely recognized in the construction industry as the go-to contract template for owner-contractor relationships.
Why the Other Options Are Wrong
Option A: AIA A201 - General Conditions
AIA A201 contains the General Conditions of the Contract for Construction, which supplements the owner-contractor agreement but is not the agreement itself. It provides detailed terms and conditions that govern the construction process but does not establish the basic contractual relationship.
Option C: AIA A401 - Contractor-Subcontractor Agreement
AIA A401 is the standard form of agreement between contractor and subcontractor, not between owner and contractor. This document governs the relationship between the general contractor and their subcontractors.
Option D: AIA A701 - Instructions to Bidders
AIA A701 provides Instructions to Bidders and is used during the bidding phase to give potential contractors information about the bidding process. It is not a contract agreement between parties.
Memory Technique
Think 'A101 = Agreement #1' - it's the primary agreement that starts the owner-contractor relationship, while A201 comes second with the detailed conditions.
Reference Hint
Look up AIA Contract Documents in construction law or contract administration chapters of your reference materials
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass