Which document would typically contain the specific scope of work, schedule, and payment terms between a general contractor and subcontractor?
Correct Answer
C) AIA A401
AIA A401 is the Standard Form of Agreement Between Contractor and Subcontractor, which contains the specific scope, schedule, payment terms, and other provisions governing the subcontract relationship.
Why This Is the Correct Answer
AIA A401 is specifically designed as the Standard Form of Agreement Between Contractor and Subcontractor. This document establishes the contractual relationship between the general contractor and subcontractor, detailing the subcontractor's scope of work, project schedule requirements, payment terms, and performance obligations. It serves as the primary governing document for subcontract work and includes provisions for coordination with the prime contract.
Why the Other Options Are Wrong
Option A: AIA A101
AIA A101 is the Standard Form of Agreement Between Owner and Contractor, which governs the relationship between the project owner and general contractor, not between contractor and subcontractor.
Option B: AIA A201
AIA A201 is the General Conditions of the Contract for Construction, which provides standard terms and conditions but is not the agreement document itself that contains specific scope, schedule, and payment terms.
Option D: Notice to Proceed
Notice to Proceed is a formal notification document that authorizes the start of work but does not contain detailed scope, schedule, or payment terms - these are established in the contract agreement.
Memory Technique
Think 'A401 = Agreement FOR ONE subcontractor' - the '4' represents the fourth party relationship (after owner, architect, contractor comes subcontractor)
Reference Hint
Florida Building Code Chapter 1, Section 107 - Construction Documents and AIA Contract Documents reference guide
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
During a rough-in inspection, the building inspector finds several code violations. What is the contractor's next required action?
Next Question
A contractor fails to call for a required inspection and covers the work. The building official discovers this during the next scheduled inspection. What enforcement action is most likely?