Under Chapter 489 F.S., what is the maximum monetary limit for a Registered Building Contractor?
Correct Answer
B) $200,000 per project and $300,000 per year
Registered Building Contractors are limited to $200,000 per individual project and $300,000 in total annual volume according to Chapter 489 F.S. These limits help distinguish between different contractor classification levels.
Why This Is the Correct Answer
Chapter 489 F.S. specifically establishes dual monetary limits for Registered Building Contractors to define their scope of work. The $200,000 per project limit ensures individual projects don't exceed a certain complexity threshold. The $300,000 annual volume limit prevents contractors from taking on too much total work beyond their registration level. These dual limits work together to maintain appropriate boundaries between different contractor classification levels.
Why the Other Options Are Wrong
Option A: $100,000 per project
$100,000 per project is too low and doesn't account for the annual volume limit that is also required by statute.
Option C: $500,000 per project
$500,000 per project exceeds the statutory limit and doesn't include the required annual volume restriction.
Option D: No monetary limit
Registered Building Contractors definitely have monetary limits - unlimited work would require a different license classification.
Memory Technique
Think '2-3 Rule': $200k per project, $300k per year - the annual limit is always $100k higher than the project limit for registered contractors.
Reference Hint
Chapter 489 Florida Statutes - Contracting License Classifications and Monetary Limits section
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass