In Florida, how long does a lienor have to file a Claim of Lien after the final furnishing of labor or materials?
Correct Answer
C) 90 days
Under Florida Statute 713.08, a Claim of Lien must be filed within 90 days after the final furnishing of labor, services, or materials by the lienor.
Why This Is the Correct Answer
Florida Statute 713.08 specifically establishes that a Claim of Lien must be filed within 90 days after the final furnishing of labor, services, or materials by the lienor. This 90-day period is a strict statutory deadline that cannot be extended. The statute is designed to provide a reasonable timeframe for lienors to perfect their lien rights while also providing certainty to property owners about when potential lien claims must be filed. Missing this 90-day deadline results in the complete loss of lien rights.
Why the Other Options Are Wrong
Option A: 45 days
45 days is too short and not the statutory requirement under Florida law
Option B: 60 days
60 days is insufficient time under Florida Statute 713.08
Option D: 120 days
120 days exceeds the statutory deadline and would be too late to file a valid lien claim
Memory Technique
Think '90 days = 3 months' - a full quarter of the year to file your lien claim, which seems like a reasonable middle ground between too short and too long
Reference Hint
Florida Statutes Chapter 713 - Construction Liens, specifically Section 713.08
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
What is the most effective way to ensure subcontractors attend weekly coordination meetings?
Next Question
In a unit price contract, the contractor bids $125 per cubic yard for concrete placement. The original estimate was 400 cubic yards, but the actual quantity installed was 475 cubic yards. What is the total payment for concrete placement?