Under California Civil Code Section 3097, what is the maximum time limit for recording a mechanics lien after completion of work on a single-family residence?

Correct Answer

B) 90 days

California Civil Code Section 3097 establishes that for single-family residences, a mechanics lien must be recorded within 90 days after completion of the work of improvement. This is different from commercial properties, which have a 90-day limit from completion of the entire project.

Answer Options
A
60 days
B
90 days
C
30 days
D
120 days

Why This Is the Correct Answer

California Civil Code establishes that mechanics liens on single-family residences must be recorded within 90 days after completion of the work of improvement. This 90-day period is the standard residential lien deadline and applies to all claimants who properly served a preliminary notice. Missing this deadline extinguishes the lien right entirely.

Why the Other Options Are Wrong

Option A: 60 days

60 days is not the statutory lien recording deadline for single-family residences in California. While 60-day periods appear elsewhere in California lien law (e.g., certain stop notice deadlines), the mechanics lien recording deadline for residential work is 90 days.

Option C: 30 days

30 days is too short and is not the lien recording deadline. A 30-day window would appear in other parts of California lien law (such as the time to respond to a notice of completion), but not as the general mechanics lien filing deadline.

Option D: 120 days

120 days exceeds the statutory period. California law does not provide a 120-day window for recording mechanics liens on single-family residences. Using 120 days would cause the lien right to be lost.

Memory Technique

90 days = one quarter of a year = your lien window. Any claimant on a California single-family residence has exactly one financial quarter to record their mechanics lien after completing work.

Was this explanation helpful?

More law-business Questions

Under B&P Code Section 7071.9, a contractor may deposit cash or securities instead of obtaining a surety bond. If a contractor chooses this option, where must the deposit be maintained and what happens to interest earned?

Under California's AB 5 law (Dynamex decision), which factor is NOT part of the ABC test for determining independent contractor status?

According to Business and Professions Code Section 7031, what is required when a licensed contractor supervises work performed by unlicensed employees on a construction project?

Under California Building Standards Code Title 24, which entity has the authority to issue building permits for most residential and commercial construction projects?

According to B&P Code 7159.5, service and repair contracts must include specific provisions. Which statement is correct regarding these contracts?

Which of the following activities is exempt from California contractor licensing requirements under Business and Professions Code Section 7048?

Under Cal/OSHA regulations in Title 8 CCR Section 5192, Safety Data Sheets (SDS) for hazardous chemicals used on construction sites must be readily accessible to employees during which hours?

Under California Business and Professions Code Section 7071.9, in lieu of a surety bond, what alternative security may a contractor provide to satisfy the contractor license bond requirement?

According to Cal/OSHA regulations, which of the following is NOT a required element of a written Injury and Illness Prevention Program (IIPP)?

A homeowner requests that a B-General Building Contractor provide a certificate of insurance naming the homeowner as an additional insured on the contractor's general liability policy. Under California law, what is the contractor's obligation?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing