EstatePass
Business & FinanceAdminmedium26% of exam part

A project requires the contractor to submit monthly payment applications. The contract value is $500,000, and 60% of the work is complete. If the contract includes 10% retention, what is the amount due to the contractor?

Correct Answer

A) $270,000

Work completed = $500,000 × 0.60 = $300,000. With 10% retention held: $300,000 - ($300,000 × 0.10) = $300,000 - $30,000 = $270,000. Retention is held until project completion.

Answer Options
A
$270,000
B
$300,000
C
$330,000
D
$450,000

Why This Is the Correct Answer

The correct answer is A) $270,000 because it properly calculates the payment due after retention. First, we determine the value of work completed (60% of $500,000 = $300,000). Then we subtract the 10% retention that the owner holds back ($300,000 × 10% = $30,000). The contractor receives $300,000 - $30,000 = $270,000. Retention is a standard practice where owners withhold a percentage of each payment until project completion to ensure contractor performance.

Why the Other Options Are Wrong

Option B: $300,000

This represents the gross value of work completed ($300,000) but fails to account for the 10% retention that must be withheld from each payment application.

Option C: $330,000

This amount doesn't correspond to any logical calculation in the retention process and appears to add rather than subtract retention.

Option D: $450,000

This represents 90% of the total contract value rather than 90% of the completed work value, ignoring that only 60% of the work is actually complete.

Memory Technique

Remember 'CPR': Complete work value, then subtract Percentage Retention. Think 'Complete first, Retain second' - you can't retain what hasn't been completed yet.

Reference Hint

Florida Building Code Chapter 1, Section 105 - Permits and Construction Documents, or AIA Contract Documents regarding payment procedures and retention

More Business & Finance Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing