In a cost-plus-fee contract, what is the contractor's primary obligation regarding project costs?

Correct Answer

B) To provide detailed documentation and accounting of all reimbursable costs

In cost-plus contracts, the contractor must maintain detailed records and provide transparent accounting of all costs since the owner reimburses actual costs plus a fee. This documentation is essential for payment and audit purposes.

Answer Options
A
To guarantee a maximum project cost
B
To provide detailed documentation and accounting of all reimbursable costs
C
To absorb any cost overruns beyond the original estimate
D
To share cost savings equally with the owner

Why This Is the Correct Answer

In cost-plus-fee contracts, the contractor is reimbursed for actual project costs plus a predetermined fee. Since the owner pays for actual costs rather than a fixed price, the contractor has a legal and contractual obligation to maintain meticulous records of all expenses. This documentation serves as proof of legitimate costs and enables proper reimbursement. Without detailed accounting, the owner cannot verify costs and the contractor cannot receive proper payment.

Why the Other Options Are Wrong

Option A: To guarantee a maximum project cost

Cost-plus contracts do not require contractors to guarantee maximum costs - that would be a guaranteed maximum price (GMP) contract. In pure cost-plus arrangements, costs can vary and the owner bears the risk of cost overruns.

Option C: To absorb any cost overruns beyond the original estimate

In cost-plus contracts, the owner, not the contractor, typically absorbs cost overruns since they reimburse actual costs. The contractor is protected from cost risk, which is why detailed documentation is so crucial for reimbursement.

Option D: To share cost savings equally with the owner

Cost savings sharing is not a standard feature of basic cost-plus contracts. This might occur in cost-plus contracts with incentive clauses, but it's not the contractor's primary obligation regarding project costs.

Memory Technique

Think 'Cost-Plus = Paperwork Plus' - the contractor gets reimbursed PLUS a fee, but only with detailed paperwork to back up every cost

Reference Hint

Construction Contract Administration chapter or Project Delivery Methods section covering cost-plus contract types

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing