A contractor submits Application for Payment #8 requesting $125,000. The contract allows 5% retainage, and $15,000 was previously retained. If this payment request is approved, what amount should the contractor receive?

Correct Answer

A) $118,750

The contractor receives the payment request minus retainage: $125,000 - (5% × $125,000) = $125,000 - $6,250 = $118,750. Previously retained amounts don't affect the current payment calculation.

Answer Options
A
$118,750
B
$115,000
C
$110,000
D
$103,750

Why This Is the Correct Answer

The correct answer is A) $118,750 because each payment application is calculated independently. The contractor receives the full payment request amount minus the current retainage percentage applied to that specific payment. The calculation is straightforward: $125,000 - (5% × $125,000) = $125,000 - $6,250 = $118,750. Previously retained amounts are tracked separately and don't reduce the current payment.

Why the Other Options Are Wrong

Option B: $115,000

This incorrectly subtracts a flat $10,000 from the payment request, which doesn't correspond to the 5% retainage calculation and appears to be an arbitrary deduction.

Option C: $110,000

This incorrectly subtracts the previously retained $15,000 from the current payment request, but previous retainage doesn't affect current payment calculations - each application is processed independently.

Option D: $103,750

This incorrectly subtracts both the current retainage ($6,250) and the previously retained amount ($15,000), double-penalizing the contractor by applying past retainage to the current payment.

Memory Technique

Think 'Each App Stands Alone' - each Application for Payment is calculated independently, with retainage applied only to that specific payment request amount.

Reference Hint

AIA Document A201 - General Conditions, Section 9.3 Applications for Payment, and Florida Statutes Chapter 713 regarding construction payments and retainage

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing