EstatePass
Contract AdminContractsmedium40% of exam part

An owner and contractor have a dispute over $45,000 in additional work. The contract specifies that disputes under $50,000 must first go to mediation before litigation. The contractor wants to file a lawsuit immediately. What should happen?

Correct Answer

B) The court will likely require mediation first per the contract terms

When a contract specifies a dispute resolution process such as mandatory mediation before litigation, courts typically enforce these provisions and require parties to follow the contractual dispute resolution procedures before allowing litigation to proceed.

Answer Options
A
The contractor can proceed directly to litigation since the amount exceeds $40,000
B
The court will likely require mediation first per the contract terms
C
The dispute must go to binding arbitration instead of court
D
Either party can choose between mediation and litigation

Why This Is the Correct Answer

Courts generally enforce contractual dispute resolution clauses as written, viewing them as valid agreements between parties. Since the contract specifically requires mediation for disputes under $50,000, and this dispute is $45,000, the mediation requirement applies. Courts will typically stay litigation proceedings until the contractual mediation process is completed, as parties are bound by the terms they agreed to in their contract.

Why the Other Options Are Wrong

Option A: The contractor can proceed directly to litigation since the amount exceeds $40,000

This option incorrectly suggests there's a $40,000 threshold that allows bypassing mediation, but the contract clearly states disputes under $50,000 must go to mediation first. The $45,000 dispute falls below the $50,000 threshold, so mediation is required regardless of any other amount.

Option C: The dispute must go to binding arbitration instead of court

The contract specifies mediation, not arbitration. These are different dispute resolution methods - mediation is non-binding facilitated negotiation, while arbitration results in a binding decision. The contract terms control what process must be followed.

Option D: Either party can choose between mediation and litigation

When a contract contains mandatory dispute resolution language (like 'must first go to mediation'), neither party has the choice to bypass this requirement. The contractual obligation is binding on both parties, and courts will enforce the agreed-upon sequence of dispute resolution.

Memory Technique

Remember 'Contract Controls Courts' - when contracts specify dispute procedures, courts typically enforce them rather than allow parties to skip agreed-upon steps.

Reference Hint

Florida Construction Law - Chapter on Contract Dispute Resolution and Alternative Dispute Resolution (ADR) provisions

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing