A project has liquidated damages of $1,500 per day and is completed 12 days late. The contractor incurred $8,000 in additional costs to accelerate the work. What is the contractor's total delay-related cost?
Correct Answer
C) $26,000
Total cost includes both the liquidated damages ($1,500 × 12 days = $18,000) and the acceleration costs ($8,000), totaling $26,000.
Why This Is the Correct Answer
The contractor's total delay-related cost includes both the liquidated damages penalty and the additional costs incurred to accelerate the work. Liquidated damages are calculated as $1,500 per day × 12 days = $18,000. The acceleration costs of $8,000 are added to this amount. Therefore, the total delay-related cost is $18,000 + $8,000 = $26,000.
Why the Other Options Are Wrong
Option A: $8,000
This only accounts for the acceleration costs ($8,000) but ignores the liquidated damages penalty of $18,000 that the contractor must pay for being 12 days late.
Option B: $18,000
This only accounts for the liquidated damages ($1,500 × 12 = $18,000) but fails to include the $8,000 in acceleration costs that the contractor also incurred.
Option D: $10,500
This appears to be an arbitrary calculation that doesn't properly account for either the full liquidated damages amount or the acceleration costs.
Memory Technique
Remember 'TOTAL = LD + AC' (Liquidated Damages + Acceleration Costs) - both penalties hit the contractor's bottom line
Reference Hint
Look up contract administration and liquidated damages clauses in construction law references or project management chapters
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
When estimating equipment costs, which factor is typically NOT considered when comparing owned versus rented equipment?
Next Question
An experienced contractor is estimating productivity for installing drywall in a high-end residential project with many angles and custom details. Compared to standard productivity rates, the adjustment factor should be: