You receive three electrical subcontractor bids: Contractor A - $45,000 (excludes permits), Contractor B - $48,500 (includes all items), Contractor C - $44,200 (excludes temporary power). The permit cost is $800 and temporary power is $1,200. Which bid should be selected based on total cost?
Correct Answer
C) Contractor C at $45,400 total
Contractor A total: $45,000 + $800 = $45,800. Contractor B: $48,500 (complete). Contractor C: $44,200 + $1,200 = $45,400. Contractor C has the lowest total cost when all items are included.
Why This Is the Correct Answer
Contractor C has the lowest total cost when all items are properly included. To make an accurate comparison, all bids must be normalized to include the same scope of work. When we add the missing temporary power cost of $1,200 to Contractor C's base bid of $44,200, the total becomes $45,400, which is lower than both Contractor A's normalized total of $45,800 and Contractor B's complete bid of $48,500.
Why the Other Options Are Wrong
Option A: Contractor A at $45,800 total
Contractor A's total cost is $45,800 ($45,000 + $800 permit), which is $400 more than Contractor C's normalized total of $45,400.
Option B: Contractor B at $48,500 total
Contractor B's bid of $48,500 is the highest total cost, being $3,100 more than Contractor C's normalized total and $2,700 more than Contractor A's normalized total.
Option D: All bids are equal when normalized
The bids are not equal when normalized - there are clear differences in total costs ranging from $45,400 to $48,500.
Memory Technique
Use 'ABC-Add Before Compare' - always Add missing costs Before Comparing bids to ensure apples-to-apples evaluation
Reference Hint
Florida Building Code Chapter 1 - Administration and Enforcement, and general contracting cost estimation sections in contractor reference materials
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass