A construction site has a 2,500 square foot building under construction. What is the minimum number of 2A:10BC fire extinguishers required?
Correct Answer
C) 3
OSHA requires one 2A:10BC fire extinguisher for every 3,000 square feet of building area under construction, but with a minimum spacing that would require 3 extinguishers for adequate coverage of a 2,500 sq ft area.
Why This Is the Correct Answer
OSHA requires one 2A:10BC fire extinguisher for every 3,000 square feet of building area under construction. However, the spacing requirements mandate that extinguishers be placed so that travel distance to reach one does not exceed 100 feet. For a 2,500 square foot building, proper coverage and accessibility requires a minimum of 3 extinguishers to ensure no point in the building is more than 100 feet from an extinguisher. This accounts for both the square footage requirement and the maximum travel distance requirement.
Why the Other Options Are Wrong
Option A: 1
One extinguisher would not provide adequate coverage for a 2,500 sq ft area, as workers could be more than 100 feet away from the single extinguisher location, violating OSHA spacing requirements.
Option B: 2
Two extinguishers may still leave areas of the building where workers would need to travel more than 100 feet to reach an extinguisher, failing to meet OSHA's maximum travel distance requirements.
Option D: 4
Four extinguishers would exceed the minimum requirement and, while not unsafe, would be unnecessary and costly for a 2,500 sq ft building area.
Memory Technique
Remember '3-100 Rule': 3,000 sq ft per extinguisher AND 100 feet maximum travel distance. When in doubt, sketch the building layout and check if anyone would walk more than 100 feet to reach an extinguisher.
Reference Hint
OSHA Construction Standards 29 CFR 1926.150 - Fire Protection, specifically subsection (c) regarding portable fire extinguishers
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
A detail drawing shows a scale of 3/4" = 1'-0". If a dimension measures 2.25 inches on the drawing, what is the actual dimension?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Previous Question
A construction site has multiple buildings under construction. What is the maximum distance between fire extinguishers for Class A (ordinary combustibles) fires?
Next Question
According to OSHA standards, Class E hard hats are designed to protect against electrical shock up to what voltage?