In arbitration proceedings for a construction dispute, the arbitrator's decision is generally:
Correct Answer
B) Binding and enforceable like a court judgment
Arbitration typically results in a binding decision that is enforceable like a court judgment. This is a key difference from mediation, where the mediator's role is to facilitate agreement rather than impose a decision.
Why This Is the Correct Answer
Arbitration produces a binding decision called an 'award' that has the same legal force as a court judgment. Once an arbitrator renders a decision, both parties are legally obligated to comply with it. The arbitrator acts as a private judge with the authority to make final, enforceable decisions. This binding nature is what makes arbitration an effective alternative dispute resolution method for construction disputes.
Why the Other Options Are Wrong
Option A: A recommendation that either party can reject
This describes mediation, not arbitration. In arbitration, the arbitrator makes a binding decision that cannot be simply rejected by either party.
Option C: Subject to appeal to a higher arbitration panel
Arbitration decisions are generally final with very limited grounds for appeal. Unlike court systems, there is no higher arbitration panel to appeal to - finality is a key feature of arbitration.
Option D: Only advisory unless both parties agree to be bound
This also describes mediation or non-binding arbitration. Standard arbitration is binding by default when parties agree to arbitrate - they don't need separate agreement to be bound by the decision.
Memory Technique
Think 'ARBitration = ARBiter = judge-like authority = BINDING decision' vs 'MEDiation = MEDiator = middle person helping negotiate = non-binding'
Reference Hint
Florida Building Code Chapter 1, Section 113 - Alternative Dispute Resolution, or Construction Law reference materials on arbitration vs. mediation
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
Which Florida contractor license classification allows work on projects with unlimited monetary value?
Next Question
A time and materials contract specifies labor at $85/hour and materials at cost plus 15%. If 40 hours of labor and $8,000 in materials are used, what is the total billing?