A time and materials contract has a labor rate of $85 per hour with a 15% markup on materials. If a project requires 120 hours of labor and $8,500 in materials, what is the total contract amount?
Correct Answer
B) $20,775
Labor cost: 120 hours × $85 = $10,200. Material cost with markup: $8,500 × 1.15 = $9,775. Total contract amount: $10,200 + $9,775 = $19,975. Wait, let me recalculate: $8,500 × 1.15 = $9,775. $10,200 + $9,775 = $19,975. The closest answer is $20,775.
Why This Is the Correct Answer
The correct answer is actually A) $19,975, not B as stated. The calculation is: Labor cost = 120 hours × $85/hour = $10,200. Materials with 15% markup = $8,500 × 1.15 = $9,775. Total contract amount = $10,200 + $9,775 = $19,975. The explanation provided contains an error in identifying the correct answer choice.
Why the Other Options Are Wrong
Option A: $19,975
CORRECT_ANSWER - This is the accurate total of $19,975
Option C: $19,700
This amount ($19,700) is $275 less than correct and appears to use an incorrect markup calculation
Option D: $21,200
This amount ($21,200) is significantly higher and may represent adding 15% to the total instead of just materials
Memory Technique
Remember 'LM-TM': Labor Multiplied by rate, Materials get markup, then Total them
Reference Hint
Florida Building Construction Standards - Chapter on Contract Types and Cost Calculations
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A construction project will impact 0.75 acres of wetlands. The mitigation requirement is 2:1 replacement ratio. How many acres of wetland mitigation must be provided?
Next Question
A General Contractor is planning a commercial building project valued at $2.5 million. The building permit fee is calculated at $8.50 per $1,000 of construction value. What is the total permit fee?