You are excavating a trench that is 8 feet deep in Type C soil. What is the minimum required slope ratio for the sides of this excavation?
Correct Answer
D) 1.5:1 (34 degrees)
For Type C soil (the least stable), OSHA requires a slope ratio of 1.5:1 (34 degrees from horizontal) to ensure worker safety in excavations.
Why This Is the Correct Answer
OSHA 29 CFR 1926.652 specifies that Type C soil, being the least stable soil classification, requires the most conservative slope ratio of 1.5:1 (34 degrees from horizontal). This means for every 1.5 feet of horizontal distance, the excavation can drop 1 foot vertically. Type C soils include granular soils, submerged soil, and soil from which water is freely seeping, all of which have poor cohesive properties and require maximum sloping for safety.
Why the Other Options Are Wrong
Option A: 1/2:1 (63 degrees)
The 1/2:1 ratio (63 degrees) is too steep and dangerous for any soil type under OSHA standards. This steep angle would not provide adequate protection against cave-ins in Type C soil.
Option B: 3/4:1 (53 degrees)
The 3/4:1 ratio (53 degrees) is the required slope for Type A soil, which is the most stable soil type. Type C soil requires a much more gradual slope due to its instability.
Option C: 1:1 (45 degrees)
The 1:1 ratio (45 degrees) is the required slope for Type B soil, which has moderate stability. Type C soil is less stable than Type B and therefore requires an even more gradual slope.
Memory Technique
Remember 'ABC = 3/4, 1, 1.5' - Type A soil uses 3/4:1, Type B uses 1:1, Type C uses 1.5:1. Think 'C is Crappy soil, needs the most Conservative slope of 1.5:1'
Reference Hint
OSHA 29 CFR 1926.652 - Requirements for protective systems, Table B-1 in Appendix B shows the maximum allowable slopes for different soil types
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
A detail drawing shows a scale of 3/4" = 1'-0". If a dimension measures 2.25 inches on the drawing, what is the actual dimension?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass