A mixed-use development requires a special use permit from the local planning commission. The contractor has already obtained a building permit. Can construction begin immediately?
Correct Answer
B) No, the special use permit must be obtained before any construction
All required permits and approvals, including special use permits, must be obtained before construction can begin. A building permit alone is not sufficient if other land use approvals are required.
Why This Is the Correct Answer
Special use permits are land use approvals that must be obtained before any construction activities can commence. These permits address zoning compliance and land use compatibility, which are fundamental requirements that supersede building permits. A building permit only authorizes the physical construction aspects but cannot override the need for proper land use authorization. All required permits and approvals must be in place before breaking ground on any project.
Why the Other Options Are Wrong
Option A: Yes, the building permit is sufficient to begin construction
A building permit alone is insufficient when additional land use approvals are required. The building permit only addresses construction standards and safety requirements, but does not grant permission to use the land for the intended purpose without proper zoning approval.
Option C: Yes, but only site preparation work can begin
Even site preparation work constitutes construction activity and cannot begin without all required permits and approvals in place. Any ground disturbance or construction-related activity requires full permit compliance, including the special use permit.
Option D: No, unless the contractor posts an additional bond
Posting an additional bond does not substitute for obtaining required permits. Bonds provide financial security but do not grant legal authorization to proceed without proper permits and approvals from the appropriate authorities.
Memory Technique
Think 'LAND FIRST' - Land use approval must come before any construction activity. Special Use = Special STOP until approved.
Reference Hint
Florida Building Code Chapter 1 - Scope and Administration, and local zoning ordinances regarding permit requirements and sequencing
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass