During a construction coordination meeting, the electrical subcontractor reports they need to relocate conduit due to a structural conflict. What should be the general contractor's first priority?
Correct Answer
B) Review the impact on other trades and the schedule
The general contractor should first assess how the electrical change will impact other trades, the project schedule, and overall coordination before making any decisions. This comprehensive review ensures all implications are understood before proceeding.
Why This Is the Correct Answer
Option B is correct because the general contractor's primary responsibility is project coordination and management. When any trade requests a change, the GC must first conduct a comprehensive impact analysis to understand how the change affects other trades, the critical path schedule, costs, and overall project coordination. This systematic review prevents cascading problems and ensures informed decision-making. Making decisions without this analysis can lead to conflicts with other trades, schedule delays, and cost overruns.
Why the Other Options Are Wrong
Option A: Approve the change immediately to avoid delays
Approving changes immediately without proper analysis is poor project management that can lead to conflicts with other trades, unforeseen costs, and schedule disruptions. The GC must understand all implications before approval.
Option C: Reject the change to maintain original design
Automatically rejecting changes without evaluation is inflexible and may ignore legitimate field conditions or conflicts that require resolution. Changes may be necessary for proper construction.
Option D: Contact the owner for additional funding
Contacting the owner for funding is premature before understanding the scope, necessity, and cost implications of the change. The impact analysis must come first to provide accurate information to the owner.
Memory Technique
Use 'AIRS' - Analyze Impact, Review Schedule, then decide. Never make immediate decisions on field changes without comprehensive review.
Reference Hint
Florida Building Code - Chapter 1 (Administration and Enforcement) and Project Management sections covering change order procedures and coordination responsibilities
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass