EstatePass
Contract AdminProceduresmedium13% of exam part

During a construction coordination meeting, the electrical subcontractor reports they need to relocate conduit due to a structural conflict. What should be the general contractor's first priority?

Correct Answer

B) Review the impact on other trades and the schedule

The general contractor should first assess how the electrical change will impact other trades, the project schedule, and overall coordination before making any decisions. This comprehensive review ensures all implications are understood before proceeding.

Answer Options
A
Approve the change immediately to avoid delays
B
Review the impact on other trades and the schedule
C
Reject the change to maintain original design
D
Contact the owner for additional funding

Why This Is the Correct Answer

Option B is correct because the general contractor's primary responsibility is project coordination and management. When any trade requests a change, the GC must first conduct a comprehensive impact analysis to understand how the change affects other trades, the critical path schedule, costs, and overall project coordination. This systematic review prevents cascading problems and ensures informed decision-making. Making decisions without this analysis can lead to conflicts with other trades, schedule delays, and cost overruns.

Why the Other Options Are Wrong

Option A: Approve the change immediately to avoid delays

Approving changes immediately without proper analysis is poor project management that can lead to conflicts with other trades, unforeseen costs, and schedule disruptions. The GC must understand all implications before approval.

Option C: Reject the change to maintain original design

Automatically rejecting changes without evaluation is inflexible and may ignore legitimate field conditions or conflicts that require resolution. Changes may be necessary for proper construction.

Option D: Contact the owner for additional funding

Contacting the owner for funding is premature before understanding the scope, necessity, and cost implications of the change. The impact analysis must come first to provide accurate information to the owner.

Memory Technique

Use 'AIRS' - Analyze Impact, Review Schedule, then decide. Never make immediate decisions on field changes without comprehensive review.

Reference Hint

Florida Building Code - Chapter 1 (Administration and Enforcement) and Project Management sections covering change order procedures and coordination responsibilities

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing