EstatePass
Contract AdminProcedureshard13% of exam part

In CPM scheduling, if an activity has an early start of day 10, duration of 5 days, and late finish of day 20, what is the activity's total float?

Correct Answer

B) 5 days

Total float = Late Finish - Early Start - Duration + 1. In this case: 20 - 10 - 5 + 1 = 6 days. However, using the standard formula: Late Finish - Early Finish = 20 - 15 = 5 days.

Answer Options
A
0 days
B
5 days
C
10 days
D
15 days

Why This Is the Correct Answer

CORRECT_ANSWER - Total float represents the amount of time an activity can be delayed without affecting the project completion date. The standard formula is Total Float = Late Finish - Early Finish, where Early Finish = Early Start + Duration. With Early Start of 10 and Duration of 5, the Early Finish is 15. Therefore, Total Float = 20 - 15 = 5 days.

Why the Other Options Are Wrong

Option A: 0 days

Zero days would indicate this is a critical path activity with no scheduling flexibility, but the calculation shows 5 days of float available.

Option C: 10 days

10 days incorrectly assumes the float equals the early start date, which has no relationship to the actual float calculation.

Option D: 15 days

15 days incorrectly assumes the float equals the early finish date (10 + 5), which is not how total float is calculated.

Memory Technique

Remember 'LEAF' - Late finish minus Early finish equals Available Float. Early finish is always Early start plus Duration.

Reference Hint

Look up CPM scheduling and float calculations in Chapter 6 (Project Scheduling) of most construction management textbooks or the PMI Practice Standard for Scheduling.

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing