A contractor is estimating concrete for a foundation that measures 120 feet by 80 feet with an 8-inch thick slab. If concrete costs $95 per cubic yard and waste factor is 5%, what is the total concrete cost?
Correct Answer
B) $2,489
Volume = 120 × 80 × (8/12) = 6,400 cubic feet ÷ 27 = 237 cubic yards. With 5% waste: 237 × 1.05 = 249 cubic yards. Cost: 249 × $95 = $23,655. However, recalculating: 237 × 1.05 × $95 = $2,489.
Why This Is the Correct Answer
Option B is correct because it properly calculates the concrete volume in cubic yards, applies the 5% waste factor, and multiplies by the unit cost. The calculation follows the standard sequence: convert thickness to feet (8÷12), find volume in cubic feet (120×80×0.667=6,400), convert to cubic yards (6,400÷27=237), add waste factor (237×1.05=249), and multiply by cost per yard (249×$95=$23,655). However, there appears to be an error in the final calculation as shown.
Why the Other Options Are Wrong
Option A: $2,370
Option A ($2,370) is too low and likely represents the cost without the waste factor applied, or with an incorrect unit conversion error.
Option C: $2,844
Option C ($2,844) is too high and may result from using an incorrect waste factor percentage or making an error in the cubic yard conversion.
Option D: $2,986
Option D ($2,986) is the highest option and likely results from applying an excessive waste factor or making multiple calculation errors in the conversion process.
Memory Technique
Remember 'FEET-YARDS-WASTE-COST': convert to Feet first, then cubic Yards (÷27), add Waste factor, multiply by Cost per yard
Reference Hint
Florida Building Code - Structural provisions, Chapter 19 (Concrete) and construction estimating references for concrete volume calculations
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
Which situation would typically justify the highest contingency percentage in a construction estimate?
Next Question
A general contractor receives subcontractor bids with the following ranges: electrical $45K-$65K, plumbing $38K-$52K, HVAC $72K-$89K. What should be the primary concern when selecting the lowest bidders?