EstatePass
Contract AdminContractseasy40% of exam part

A general contractor receives a change order request that will add $25,000 to the project cost and 10 days to the schedule. Before proceeding, the contractor must:

Correct Answer

B) Obtain written approval from the owner before starting the work

Change orders should be properly documented and approved in writing before work begins to avoid disputes over scope, cost, and time adjustments. This protects both the contractor and owner.

Answer Options
A
Immediately begin the additional work
B
Obtain written approval from the owner before starting the work
C
Complete the work and bill it as an extra
D
Refuse the change order to avoid delays

Why This Is the Correct Answer

Option B is correct because proper change order procedures require written documentation and owner approval before any additional work begins. This protects both parties by clearly establishing the scope, cost, and time implications of the change. Without written approval, contractors risk not being paid for extra work or facing disputes over what was actually authorized. Florida construction law and standard industry practices emphasize the importance of documented change orders to avoid costly litigation.

Why the Other Options Are Wrong

Option A: Immediately begin the additional work

Starting work immediately without written approval is dangerous and can lead to payment disputes, as the contractor has no legal protection if the owner later refuses to pay for unauthorized work.

Option C: Complete the work and bill it as an extra

Completing work first and billing as an extra afterward puts the contractor at significant financial risk, as there's no guarantee the owner will pay for work that wasn't pre-approved in writing.

Option D: Refuse the change order to avoid delays

Automatically refusing change orders is poor business practice and may violate contractual obligations to consider reasonable changes requested by the owner.

Memory Technique

Use the acronym 'WRITE' - Written approval Required before Initial Task Execution

Reference Hint

Florida Building Code Chapter 1, Section 105 - Construction Documents and Chapter 489 Florida Statutes regarding contractor licensing and change order requirements

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing