A building permit fee calculation includes a base fee of $125 plus $0.75 per square foot for a 4,200 square foot residence. Additionally, there is a 3% processing fee on the total. What is the final permit cost?

Correct Answer

D) $3,372.25

Base fee: $125. Square footage fee: 4,200 × $0.75 = $3,150. Subtotal: $125 + $3,150 = $3,275. Processing fee: $3,275 × 0.03 = $98.25. Total: $3,275 + $98.25 = $3,373.25.

Answer Options
A
$3,400.00
B
$3,502.00
C
$3,275.00
D
$3,372.25

Why This Is the Correct Answer

Option D correctly follows the three-step permit fee calculation process. First, calculate the square footage fee (4,200 × $0.75 = $3,150), then add the base fee ($125 + $3,150 = $3,275), and finally apply the 3% processing fee ($3,275 × 0.03 = $98.25) for a total of $3,373.25. This systematic approach ensures all fee components are properly included in the final calculation.

Why the Other Options Are Wrong

Option A: $3,400.00

This amount is far too high and doesn't follow any logical calculation sequence for the given parameters.

Option B: $3,502.00

This amount appears to include some components but doesn't properly account for all fees in the correct sequence.

Option C: $3,275.00

This represents only the subtotal before the 3% processing fee is applied ($125 base + $3,150 square footage fee), missing the final processing fee calculation.

Memory Technique

Remember 'BPS' - Base fee + Per square foot fee = Subtotal, then add Processing fee. Always calculate percentage fees on the subtotal, not individual components.

Reference Hint

Florida Building Code Chapter 1 - Scope and Administration, Section 105 (Permits) for fee structures and calculations

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing