A contractor notices a discrepancy between the architectural drawings and structural drawings regarding beam sizes. What should be the first course of action?
Correct Answer
C) Submit a Request for Information (RFI) to the design team
When discrepancies exist between drawings, the contractor should submit an RFI to clarify the conflict rather than making assumptions. This protects all parties and ensures proper design intent.
Why This Is the Correct Answer
Submitting an RFI is the proper protocol when discrepancies exist between contract documents. This formal process ensures the design team can clarify their intent and provide written direction. Making assumptions about beam sizes could lead to structural inadequacy or costly over-engineering, and the contractor would bear liability for any incorrect decisions. The RFI process protects all parties by documenting the issue and obtaining official clarification.
Why the Other Options Are Wrong
Option A: Use the larger beam size shown on either drawing
Simply choosing the larger beam size is an assumption that could lead to unnecessary costs and may not address the actual design intent. The larger beam might not be structurally appropriate for the specific application, and this approach bypasses proper communication protocols.
Option B: Follow the architectural drawings since they were issued first
The order in which drawings were issued does not determine precedence when there are conflicts. Architectural drawings and structural drawings serve different purposes, and structural elements should be verified through proper channels rather than assumed based on issue dates.
Option D: Use engineering judgment to select the appropriate beam
Contractors should not use their own engineering judgment to resolve conflicts between design documents unless they are licensed engineers and have been contracted to provide design services. This approach assumes liability that belongs to the design team and could violate licensing requirements.
Memory Technique
RFI = 'Resolve First, Install' - always resolve discrepancies before proceeding with installation
Reference Hint
Florida Building Code, Chapter 1 - Administration and Enforcement, sections on construction documents and approved plans
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
A detail drawing shows a scale of 3/4" = 1'-0". If a dimension measures 2.25 inches on the drawing, what is the actual dimension?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Previous Question
A roof truss manufacturer specifies that trusses can only be lifted at designated lift points. The general contractor's crew wants to lift them at the peak for convenience. What should be done?
Next Question
According to OSHA 29 CFR 1926.501, at what height must fall protection be provided for employees working on walking/working surfaces with unprotected sides and edges?