Business & FinanceRegulationseasy15% of exam part

Construction activities begin at 6:00 AM and the site is 1.8 acres. The NPDES permit requires daily inspections. If inspections take 30 minutes and must be completed before 8:00 AM, what is the latest time inspections can begin?

Correct Answer

C) 7:30 AM

If inspections must be completed by 8:00 AM and take 30 minutes, they must begin no later than 7:30 AM. Daily inspections are required for sites over one acre under NPDES permits.

Answer Options
A
7:00 AM
B
7:15 AM
C
7:30 AM
D
7:45 AM

Why This Is the Correct Answer

This is a simple time calculation problem. If the inspection must be completed by 8:00 AM and takes 30 minutes to perform, then working backwards from the deadline gives us the latest start time. 8:00 AM minus 30 minutes equals 7:30 AM as the latest possible start time to meet the requirement.

Why the Other Options Are Wrong

Option A: 7:00 AM

7:00 AM would allow 60 minutes for the inspection, which is 30 minutes more than needed. While this would meet the requirement, it's not the latest possible start time.

Option B: 7:15 AM

7:15 AM would allow 45 minutes for the inspection, which is 15 minutes more than the required 30 minutes. This would work but is not the latest possible start time.

Option D: 7:45 AM

7:45 AM would only allow 15 minutes for the inspection, which is insufficient since the inspection requires 30 minutes to complete properly.

Memory Technique

Remember 'Deadline minus Duration equals latest Start time' - use the formula D - D = S for time management problems

Reference Hint

Environmental regulations chapter covering NPDES permit requirements and stormwater management compliance

More Business & Finance Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing