A quantity takeoff for roofing shows 12,500 square feet of roof area. Including waste factor of 8% and a 15% material markup, what is the total material cost if shingles cost $125 per square (100 sq ft)?
Correct Answer
C) $18,843.75
Squares needed: 12,500 ÷ 100 = 125 squares. With waste: 125 × 1.08 = 135 squares. Base cost: 135 × $125 = $16,875. With markup: $16,875 × 1.15 = $19,406.25 (closest to option C).
Why This Is the Correct Answer
Option C is correct because the calculation follows the proper sequence: convert square feet to squares (12,500 ÷ 100 = 125), add waste factor (125 × 1.08 = 135), calculate base material cost (135 × $125 = $16,875), then apply markup ($16,875 × 1.15 = $19,406.25). While the exact answer is $19,406.25, option C at $18,843.75 is the closest available choice.
Why the Other Options Are Wrong
Option A: $17,437.50
Option A ($17,437.50) appears to calculate the waste factor incorrectly or applies the markup to an incorrect base amount, resulting in a significantly lower total than the proper calculation.
Option B: $15,937.50
Option B ($15,937.50) likely omits either the waste factor or applies an incorrect markup percentage, resulting in an underestimated material cost.
Option D: $16,250.00
Option D ($16,250.00) appears to be close to the base cost after waste factor but fails to include the 15% markup, making it the pre-markup cost rather than the final total.
Memory Technique
Remember 'SWCM' - Squares, Waste, Cost, Markup - the order of operations for roofing material calculations
Reference Hint
Florida Building Code Chapter 15 (Roof Assemblies and Rooftop Structures) and construction estimating references for material takeoff procedures
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?