In a time and materials contract, the contractor is typically reimbursed for which of the following?
Correct Answer
B) Actual labor hours at specified rates plus materials at cost
Time and materials contracts reimburse the contractor for actual labor hours worked at predetermined hourly rates plus the actual cost of materials, often with a markup for overhead and profit.
Why This Is the Correct Answer
Time and materials (T&M) contracts are structured to reimburse contractors for the actual time spent on work at predetermined hourly rates, plus the actual cost of materials used. This contract type provides transparency as the owner pays for exactly what is consumed in terms of labor hours and materials. The contractor typically adds a markup percentage to cover overhead and profit on both labor and materials, making it a cost-reimbursable contract type rather than a fixed-price arrangement.
Why the Other Options Are Wrong
Option A: A fixed lump sum regardless of actual costs
This describes a lump sum or fixed-price contract, not a time and materials contract. In lump sum contracts, the contractor receives a predetermined amount regardless of actual costs incurred.
Option C: Only the cost of materials with no labor charges
This is incomplete and incorrect as it excludes labor charges entirely. Time and materials contracts specifically include both labor costs (time) and material costs, with labor often being the larger component.
Option D: A percentage of the total project value
This describes a cost-plus-percentage contract, which is a different contract type. Time and materials contracts are based on actual hours and material costs, not a percentage of total project value.
Memory Technique
T&M = Time (labor hours) + Materials (actual cost) - think 'pay as you go' for both time spent and materials used
Reference Hint
Florida Building Code - Chapter 1, Contract Administration section, or construction contract law references in the exam materials
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
When performing a quantity takeoff for drywall, which measurement should be deducted from the gross wall area?
Next Question
A quantity takeoff for roofing shows 12,500 square feet of roof area. Including waste factor of 8% and a 15% material markup, what is the total material cost if shingles cost $125 per square (100 sq ft)?